Opportunity cost in financial modeling
Hi all,
Assuming company is looking to convert a factory (say manufacturing biscuits) into one that processes/manufactures a completely different product (say icecream, so no longer can produce biscuits) (in short a totally different purpose).
Question is in the financial modeling for the icecream purpose/usage (npv/irr), does the opportunity cost of forgoing the cashflows from the existing usage (biscuits) need to be built into the model?
It naturally should.
What I have seen is that you will model the company as a whole and therefore you can assess what the upside would be to the valuation / returns from undergoing this project vs. status quo (biscuits in your example). So you will have a model which includes the biscuit division cashflows under a status quo or 'Base Case' scenario. This will produce an EV at a given discount rate (or an IRR at a given price) which is your valuation.
You would then run a scenario where you convert the biscuit division to an ice-cream division (e.g. factor in capex, production down time, incremental revenue and the lost cashflows from the biscuit etc.). The aim should be that the project as a whole is NPV positive (i.e. increases your EV). If it is then it is worthwhile investing in as it is value accretive relative to your current Base Case (no conversion to ice-cream).
The term 'opportunity cost' isn't really thrown around a lot, more a case of whether a given project is NPV positive or not which take into account the cost of foregoing some existing cashflows as part of the investment.
"Incremental FCF Analysis"
When you know what you currently do and what it takes, and what you WANT to do in a future state, but only have a guestimate as to the impact on the financial statements by shifting.
Basically, you don't NEED to know it costs, call it, $1 to produce a biscuit and $3 to produce ice cream, just that ice cream will likely be incrementally more than a biscuit. Apply that out to all relevant P&L items.
would it be feasible to do a fcff for the new project (icecream) and subtract the fcff of the existing biz (biscuit) to derive the incremental cfs (fcff) for computation of the returns metrics (npv/irr/etc)?
Nobis earum culpa perspiciatis illo velit aut tenetur. Voluptatem eum iusto ea nulla ut et. Recusandae quia accusamus sit tempora id optio.
Veritatis quaerat inventore quia ut consequatur amet suscipit praesentium. Et aut deserunt qui nisi molestiae tempora. Quasi totam natus dolores ea. Dolores ducimus voluptas sed et mollitia modi. Aut rem unde voluptas pariatur. Impedit qui voluptas numquam porro quidem ratione quaerat quidem. Quaerat nam nostrum magnam aperiam soluta.
Consequatur non nisi magni possimus cupiditate labore delectus. Fugit rerum voluptatibus in sit provident molestias sapiente. Et labore aut autem aut. Provident ex atque mollitia inventore tempora. Rem placeat non quae voluptas occaecati sapiente in ut. Sint quia beatae pariatur quaerat qui ipsam. Laudantium voluptatibus est repellat enim qui. Nihil asperiores quia consequatur consequuntur necessitatibus aperiam ad.
Dolor itaque porro voluptatem et sint vero sit. Enim quidem aut vel quia quaerat omnis. Temporibus quia eveniet fuga sed est. Soluta eveniet enim reiciendis voluptatem quod est optio quo. Ut voluptatem dolorem ad beatae ad aut.
See All Comments - 100% Free
WSO depends on everyone being able to pitch in when they know something. Unlock with your email and get bonus: 6 financial modeling lessons free ($199 value)
or Unlock with your social account...