Developer Fee Contributed As Equity

I am having a hard time understanding the logic of allowing developers to count their fee in required equity.

Conceptionally, all equity should go in before the senior debt. Allowing them to put in $1-3MM as non-cash effectively increases your risk profile with no offset.

How are teams getting comfortable with allowing developers to do this?

How do you model this? i.e. how is the developer fee draw paid and to whom?

13 Comments
 
"sk8247365" Let's say you are 12 months into a 24 month construction (drawing on the senior loan) and the developer leaves.

They "contributed" their fee, so all equity is "in" and you have to find another developer

That new developer is going to expect loan draws to start funding a percentage of completion fee, right? Wouldn't you have a gap in the capital stack?

Sure, but the odds you're selling that half finished building at par are... minimal. The new developer is going to bid 75 cents on the dollar and capitalize their developer fee. Since you as the senior lender just wiped out a ton of equity, you're not losing on this either.

And if it's economic conditions causing the original developer to abandon... well, it's a question of what you think motivates developers. Under the traditional model, that developer can walk away with a substantial portion of their developer fee and leave you the site, meaning you still have a problem. Maybe you don't have quite as large of a "gap", but by withholding all fee from a developer until you're loan is taken out on completion, you remove any possible incentive to walk from a project.

 
Most Helpful
"VolatilitySmile" Can you break down what this looks like for an LP/GP equity situation? For example what do you mean by "selling at par" ? I imagine if the GP quits, then the GP equity that was invested up front becomes the LP's? And then the LP gets another GP to "bid" on the equity abandoned by the original GP?

Put very briefly, if I am Developer A, and I am building my project for a $100mm total development cost, I have probably raised somewhere in the region of 35-40mm of that in equity (60-65% financed).

If my lender takes back the keys, my equity position gets absorbed by the bank. Two advantages to that. One, is that if my building is 50% built, it means that 35mm of my money is poured into it and only 15mm of the bank's, because equity is almost always the first dollars out the door in construction projects. Second, my lender is now sitting on a "basis" of 65mm. They own the property, and their investment in it was only 65mm. Assuming that the cost overruns haven't been truly absurd or the market truly atrocious, that means the bank is sitting on an asset worth substantially more than their basis in the project.

So when I say "selling at par" I mean the bank is not selling that half finished building at a $100mm valuation. They're selling it at an 80mm valuation. There are additional costs to restart the process halfway through, but that still represents a real discount to market for Developer B who buys it at a distressed asset auction. That probably includes restructuring the existing debt as well, so Developer B can still take a fee under the new financing structure, too.

 

I don't think you understand the concept fully, if you are discussing paying the developer fee through draws/requisitions.

The fee is part of the whole capital stack but never gets drawn. So there is no difference to the risk profile for the lender. In fact, it can be less risky. Think about developers who go an syndicate out all their equity and keep their fee. That's a borrower who is, from the perspective of a lender, able to walk away with little financial downside. If that developer is investing their fee in the deal you know they're less likely to walk.

 
"sk8247365" If you do not allow the fee to be contributed, they have to invest cash equity. Allowing it reduces their cash equity contribution, as the fee is more along the lines of sweat equity (at least up front).

Cash is cash. In the traditional model, the developer gets paid a cash fee. Aside from the slight value of that money being paid out over time vs up front, what's the difference? It may be booked differently but at the end of the day that money is coming from the borrower either way. What do you care where it comes from? From the perspective of a senior lender, having the dev fee be part of the capital stack means ensuring that your borrower is actually putting in real money.

 

Piggybacking, feel free to have me start a new topic. Would this be the same as an "acquisition fee" and is this common for younger people just getting their start?

In other words, I want to start investing in properties but don't have nearly the capital to be considered a serious partner. How would you structure my equity contribution as an acquisition fee that gets lumped into the capital stack as a way of paying for all of the legwork to structure the deal and have it close?

 

Atque dolore eos error aut voluptas. Blanditiis quia sint delectus expedita ipsa quisquam voluptate similique. Consequatur consectetur qui perferendis facere qui ea.

Maxime velit ut quas distinctio commodi. Iusto voluptas alias illo quam corrupti atque iure. Quasi quis nisi vero pariatur et dolor omnis molestiae.

Doloribus quidem consequatur nam delectus vel aut. A in quis facere soluta recusandae possimus. Perferendis voluptas omnis non totam velit. Consequuntur commodi omnis voluptatem quas facere tenetur qui. Corporis autem saepe aut reprehenderit quos labore.

Nisi dolorem perferendis qui et. Enim nulla nesciunt quisquam aspernatur voluptas non. Dolores rerum consequatur sit aut debitis veniam commodi.

Career Advancement Opportunities

June 2026 Investment Banking

  • Evercore 01 99.4%
  • Moelis & Company 01 98.8%
  • JPMorgan 01 98.2%
  • Guggenheim Partners 01 97.7%
  • Morgan Stanley 07 97.1%

Overall Employee Satisfaction

June 2026 Investment Banking

  • Moelis & Company No 99.4%
  • Morgan Stanley 02 98.8%
  • Evercore 01 98.2%
  • BMO Capital Markets 12 97.6%
  • Banco Santander 01 97.1%

Professional Growth Opportunities

June 2026 Investment Banking

  • Evercore 01 99.4%
  • Moelis & Company 01 98.8%
  • Morgan Stanley 05 98.2%
  • JPMorgan No 97.7%
  • BMO Capital Markets 12 97.1%

Total Avg Compensation

June 2026 Investment Banking

  • Vice President (14) $434
  • Associates (43) $259
  • 3rd+ Year Analyst (8) $210
  • 2nd Year Analyst (22) $179
  • Intern/Summer Associate (13) $156
  • 1st Year Analyst (77) $151
  • Intern/Summer Analyst (71) $101
notes
16 IB Interviews Notes

“... there’s no excuse to not take advantage of the resources out there available to you. Best value for your $ are the...”

Leaderboard

1
redever's picture
redever
99.2
2
BankonBanking's picture
BankonBanking
99.0
3
Secyh62's picture
Secyh62
99.0
4
kanon's picture
kanon
99.0
5
DrApeman's picture
DrApeman
98.9
6
dosk17's picture
dosk17
98.9
7
Betsy Massar's picture
Betsy Massar
98.9
8
GameTheory's picture
GameTheory
98.9
9
CompBanker's picture
CompBanker
98.9
10
Linda Abraham's picture
Linda Abraham
98.8
success
From 10 rejections to 1 dream investment banking internship

“... I believe it was the single biggest reason why I ended up with an offer...”