Data Center Land Development

Can anyone share info about data center land development.. Sounds like an hidden gem right now. People are buying cheap farm land, getting it rezoned/approved for a data center, and then selling it for $1m plus per acre to a developer(without actually developing anything). Can someone explain the downsides/why this is more complex than it appears. 

9 Comments
 

Can’t speak for the US but in Europe, no DC developper is actually going to buy the land until they have secured power and signed an agreement with the public utility provider. This could be relatively easy or quite difficult depending on surrounding infra and the saturation of the power network.

Then they also consider overall location (you don’t want to be too close to other people but not too far away), fiber connection points, local juridiction…

So the potential suitable plots might appear to be many but in the end the actual plot that do get built on are quite few.

Just my 2 cents from someone in the industry but without the formal finance/RE background.

 

That’s dead on from what I’ve seen in the US. Can’t speak from the development side, but I’m involved in the investment sales side on a 250+ acre data center parcel and have done extensive research on the market. Crucial thing is the load letter from the energy provider. In my experience, normally they will give you a load stating they can provide xxx on xyz date, and sometimes a ramp up from there to your long term load. Water is also a necessary utility and sometimes can be tricky or expensive to sort out.

I have a few friends who are industrial developers that have thought about trying to do the DD on a piece of dirt then flipping it to a developer. None have done anything yet because it seems almost too easy in some cases and it’s uncharted for many.

 

That article is more about construction/dev. costs. I more thinking about the land flipping play where you don't actually develop anything. Appreciate the help though!

 
Most Helpful

My team explored a couple of these, just going a little further with actually powering the land before flipping to a developer or staying in ourselves - our main concern was around power as many have mentioned. For us to get comfortable the land needed to be in direct proximity to a high KV transmission line (ideally upstream so it was cheaper from the utility), but really the main thing is switchgear and acceptance from the utility. Their load studies (market and utility dependent) had extreme lead times, not to mention the lead times for switchgear and other actual hard power equipment to get the line to the site. One of the MFs for example has been stockpiling that since '20 and some of the others bought into switchgear manufacturers to jump the line.

These were things that came up in the land stage alone - I think it's critical to be able to see the rest of the path from day 1 to avoid jumping in on something that sounds cool but doesn't work. This project ended up dying on the vine despite having land locked up at a price that would theoretically work for industrial as a last resort. We ended up stepping away due to discomfort with the space in general.

 

It isn’t just the presence of a line, but also a line that can carry more power. The ideal data center site from a power perspective would be somewhere that a utility has an excess of generation but no load to use that power.

The capacity of the wires is going to be a major factor as to how much power a site can get and what kind of upgrades will be needed to get power up and running.

There has been a lot written about the interconection queue on the renewable generation side of things, but it holds true for users as well as generators or energy.

 

Vitae corrupti minus odio asperiores dolores sed beatae odit. Eos sunt sed et. Sed debitis non qui consequatur perspiciatis odit aut. Soluta dignissimos dolores quasi sed temporibus velit. Dolor quis voluptas mollitia. Fugiat minus cupiditate quo id a eligendi sed.

Non qui quos modi maxime. Placeat ad nam delectus voluptatem quia voluptatem sit beatae. Fugiat quo iusto illo rem praesentium rerum. Sint necessitatibus omnis et cumque ipsam.

Career Advancement Opportunities

June 2026 Investment Banking

  • Evercore 01 99.4%
  • Moelis & Company 01 98.8%
  • JPMorgan 01 98.2%
  • Guggenheim Partners 01 97.7%
  • Morgan Stanley 07 97.1%

Overall Employee Satisfaction

June 2026 Investment Banking

  • Moelis & Company No 99.4%
  • Morgan Stanley 02 98.8%
  • Evercore 01 98.2%
  • BMO Capital Markets 12 97.6%
  • Banco Santander 01 97.1%

Professional Growth Opportunities

June 2026 Investment Banking

  • Evercore 01 99.4%
  • Moelis & Company 01 98.8%
  • Morgan Stanley 05 98.2%
  • JPMorgan No 97.7%
  • BMO Capital Markets 12 97.1%

Total Avg Compensation

June 2026 Investment Banking

  • Vice President (14) $434
  • Associates (43) $259
  • 3rd+ Year Analyst (8) $210
  • 2nd Year Analyst (22) $179
  • Intern/Summer Associate (13) $156
  • 1st Year Analyst (77) $151
  • Intern/Summer Analyst (71) $101
notes
16 IB Interviews Notes

“... there’s no excuse to not take advantage of the resources out there available to you. Best value for your $ are the...”

Leaderboard

1
redever's picture
redever
99.2
2
Secyh62's picture
Secyh62
99.0
3
kanon's picture
kanon
99.0
4
BankonBanking's picture
BankonBanking
99.0
5
GameTheory's picture
GameTheory
98.9
6
dosk17's picture
dosk17
98.9
7
DrApeman's picture
DrApeman
98.9
8
Betsy Massar's picture
Betsy Massar
98.9
9
CompBanker's picture
CompBanker
98.9
10
Mimbs's picture
Mimbs
98.8
success
From 10 rejections to 1 dream investment banking internship

“... I believe it was the single biggest reason why I ended up with an offer...”